20 Key Project
Manager Actions and Results
The Project
Manager's Partner by
Michael Greer is organized around these 20 Key Project Manager
Actions and Results. The handbook provides several pages of
background information concerning each of the actions, as well as
step-by-step guidelines, worksheets, and examples for helping new
project managers achieve results quickly and easily.
The 20 Key Project Manager Actions are
organized according to their support of the Five Essential
Project Management Processes: initiating, planning, executing,
controlling, and closing.
(Get here by mistake?
Return
to Michael Greer's Project Management Resources home page.)
Action
|
Results of
Successful Performance
|
Initiating
|
| 1. Demonstrate project
need and feasibility. |
 | A document confirming that there
is a need for the project deliverables and
describing, in broad terms: the deliverables,
means of creating the deliverables, costs of
creating and implementing the deliverables,
benefits to be obtained by implementing the
deliverables. |
|
| 2. Obtain project
authorization. |
 | A "go/no go" decision is
made by the sponsor. |
 | A project manager is assigned. |
 | A "project charter" is
created which:
 | Formally recognizes the
project |
 | Is issued by a manager
external to the project and at a high
enough organizational level so that he or
she can meet project needs |
 | Authorizes the project
manager to apply resources to project
activities |
|
|
| 3. Obtain authorization
for the phase. |
 | A "go/no go"
decision is made by the sponsor which authorizes
the project manager to apply organizational
resources to the activities of a particular phase
|
 | Written approval of the phase is
created which
 | Formally recognizes
the existence of the phase |
 | Is issued by a manager
external to the project and at a high
enough organizational level so that he or
she can meet project needs |
|
|
Planning
|
| 4. Describe project
scope. |
 | Statement of project scope |
 | Scope management plan |
 | Work breakdown structure |
|
| 5. Define and sequence
project activities. |
 | An activity list (list of all
activities that will be performed on the project)
|
 | Updates to the work breakdown
structure (WBS) |
 | A project network diagram |
|
| 6. Estimate durations for
activities and resources required. |
 | Estimate of durations (time
required) for each activity and assumptions
related to each estimate |
 | Statement of resource requirements
|
 | Updates to activity list |
|
| 7. Develop a project
schedule. |
 | Project schedule in the form of
Gantt charts, network diagrams, milestone charts,
or text tables |
 | Supporting details, such as
resource usage over time, cash flow projections,
order/delivery schedules, etc. |
|
| 8. Estimate costs. |
 | Cost estimates for completing each
activity |
 | Supporting detail, including
assumptions and constraints |
 | Cost management plan describing
how cost variances will be handled |
|
| 9. Build a budget and
spending plan. |
 | A cost baseline or time-phased
budget for measuring/monitoring costs |
 | A spending plan, telling how much
will be spent on what resources at what time |
|
| 10. Create a formal
quality plan. (optional) |
 | Quality management plan, including
operational definitions |
 | Quality verification checklists |
|
| 11. Create a formal
project communications plan. (optional) |
 | A communication management plan,
including:
 | Collection structure |
 | Distribution structure |
 | Description of information
to be disseminated |
 | Schedules listing when
information will be produced |
 | A method for updating the
communications plan |
|
|
| 12. Organize and acquire
staff. |
 | Role and responsibility
assignments |
 | Staffing plan |
 | Organizational chart with detail
as appropriate |
 | Project staff |
 | Project team directory |
|
| 13. Identify risks and
plan to respond. (optional) |
 | A document describing potential
risks, including their sources, symptoms, and
ways to address them |
|
| 14. Plan for and acquire
outside resources. (optional) |
 | Procurement management plan
describing how contractors will be obtained |
 | Statement of work (SOW) or
statement of requirements (SOR) describing the
item (product or service) to be procured |
 | Bid documents, such as RFP
(request for proposal), IFB (invitation for
bid),etc. |
 | Evaluation criteria -- means of
scoring contractor's proposals |
 | Contract with one or more
suppliers of goods or services |
|
| 15. Organize the project
plan. |
 | A comprehensive project plan that
pulls together all the outputs of the preceding
project planning activities |
|
| 16. Close out the project
planning phase. |
 | A project plan that has been
approved, in writing, by the sponsor A
"green light" or okay to begin work on
the project |
|
| 17. Revisit the project
plan and replan if needed. |
 | Confidence that the detailed plans
to execute a particular phase are still accurate
and will effectively achieve results as planned. |
|
Executing
|
| 18. Execute project
activities. |
 | Work results (deliverables) are
created. |
 | Change requests (i.e., based on
expanded or contracted project) are identified. |
 | Periodic progress reports are
created. |
 | Team performance is assessed,
guided, and improved if needed. |
 | Bids/proposals for deliverables
are solicited, contractors (suppliers) are
chosen, and contracts are established. |
 | Contracts are administered to
achieve desired work results. |
|
Controlling
|
| 19. Control project
activities. |
 | Decision to accept inspected
deliverables |
 | Corrective actions such as rework
of deliverables, adjustments to work process,
etc. |
 | Updates to project plan and scope |
 | List of lessons learned |
 | Improved quality |
 | Completed evaluation checklists
(if applicable) |
|
Closing
|
| 20. Close out project
activities. |
 | Formal acceptance, documented in
writing, that the sponsor has accepted the
product of this phase or activity. |
 | Formal acceptance of contractor
work products and updates to the contractor's
files. |
 | Updated project records prepared
for archiving. |
 | A plan for follow-up and/or
hand-off of work products |
|
From The Project
Manager's Partner ©
Copyright 1996, 2001 Michael Greer & HRD Press

Do you like this tool? The latest edition of The Project Manager's Partner: A Step-by-Step
Guide to Project Management contains 57 tools, checklists, and
guidelines to help project managers. For more information, click on the link
above or phone HRD Press at
(800) 822-2801.
Would you like a custom-tailored, on-site PM
workshop for your organization? Click
here to check out the possibilities or send an e-mail to greers_pm@yahoo.com.

(C) This article
copyright 2004 from Michael Greer's
Project Management Resources web site.
The URL is http://www.michaelgreer.com.
For more information, send e-mail to greers_pm@yahoo.com. -- Feel free to copy and distribute for
informational (not-for-profit) purposes.
Return to Michael Greer's Project Management
Resources home page.
|